fluid flow logo

FluidFlow helped Cochin Shipyard Ltd achieve significant cost savings and prevent further rework in the already constrained plant area.

Cochin Shipyard

Company Profile:

Cochin Shipyard Ltd India is one of the top integrated marine building, repair and training services companies and India’s most respected commercial & defence ship and offshore structure building facility. www.cochinshipyard.com

Projects Overview:

The IRClass (Indian Register of Shipping), a leading Classification society and member of IACS, has just completed the new construction survey of the MV Indira Point which was completed two months ahead of schedule at a cost of approximately USD 25 million. 

 This vessel is a high value, technologically sophisticated Buoy Tender multi-purpose vessel built by Cochin Shipyard Ltd (India) under single class. The new vessel MV Indira Point, 72 mts long, 1350 tons DWT, fitted with Heli-deck and a 35 tons capacity crane for handling buoys in deep seas was handed over to the Directorate General of Light Houses and Light Ships (DGLL India) in April 2015. IRClass Chairman and Managing Director (CMD) Mr Arun Sharma said “This single class project and its successful completion represents a major step forward for IRClass”.

 

Shipyard Fluidflow

Challenges

To evaluate the operating performance of an existing pumped sea water fire fighting system serving a heli-deck, determine the plant limitations based on a revised system layout, identify any changes required and potential plant optimisation opportunities. 

As per the contract specification for the vessel, a helicopter deck with D-Value of 16 meters was to be arranged above the forecastle deck and helideck to meet the requirements of DNV (Class). DNV Rules for classification of ships Pt.6 Ch.1 Sec.2 E301 states, a fixed foam application system consisting of either monitors or pop up nozzles with minimum capacity of at least 6 l/m2/min shall has to be provided. The system must be able to cover the whole of the helicopter landing area and have sufficient foam medium to enable the foam application rate to be maintained for at least 5 minutes.

A fixed foam application system consisting of pop-up nozzles and foam skid connects with a sea water supply assembly installed onboard the vessel as per the above CLASS requirements. As per the foam system design, there was a minimum flow requirement of 90 m3/hr of sea water and the pressure required at the foam skid was 8 bar.

FluidFlow & Cochin Shipyard Ltd

By using FluidFlow, the team at Cochin Shipyard was able to predict the performance of the upgraded system whilst retaining the existing circulating pump.

The vessel had an existing ballast pump that was capable of 150 m3/hr at 9 bar. The team at Cochin Shipyard Ltd checked the suitability of the existing pump for this upgraded application using FluidFlow. The reworked pipes and fittings were modeled together with pump performance data which was provided by the pump manufacturer. Figure 1 above provides an illustration of the overall system.

FluidFlow Cochin

Figure 1: Fire Fighting System (Final Design)

FluidFlow helped Cochin Shipyard Ltd:

Cochin Shipyard Ltd

“We use the Liquid, Gas, Dynamic Analysis Scripting of FluidFlow and make extensive use of its simulation capabilities for engineering systems as cooling water, fuel oil, ventilation, etc. Before we bought we carried out extensive product research and chose FluidFlow because of its completeness and value for money. We have also received excellent support from the FluidFlow team. We have found the FluidFlow team to be extremely knowledgeable and helpful, really excellent.”

Arun Kumar
V-Machinery Design

"

"

FluidFlow Shipyard

Impact

Engineers were able to establish that the existing pump could be successfully re-used, thus avoiding the need for an additional pump which was not anticipated during the project signing stage. This helped the team avoid further rework to the existing plant which is installed in a constrained area saving more time and revenue.

The design team achieved considerable cost savings which had not been anticipated at the project outset.

fluid flow process performance check

Start saving with Fluidflow

Ready to start your next project and achieve cost savings results?